Key House - week beginning 7 June

As we move into June the roof, first and second floor windows are all completed so the scaffolding has come down. Work starts on the outside drainage, the redevelopment of the front entrance, the original fire escape comes down and what's this, an elephant has been found trapped in the building!

Take a look at the leatest video and pictures below...

 

 To see the latest video update from Dave Downer click here.

Progress report meeting in the site office...

 

...whilst Pete Warner works away on the first floor.

Outside, the original fire escape will be going soon...

...the scaffolding has all gone but some windows are still needed...

...but at the front of the building they are all in.

On the other side of the building work begins on the drianage system.

The new doors and windows for the music room.

New windows into the new art room...

...but still waiting for these windows to go in.

On Sarum Hill, work begins on changeing the entrance area.

Later in the week the original fire escape is removed...

...and the last lot of windows go in.

What's this...it would appear that an elephant has got stuck in the building.